Category Archives: Construction Updates
Construction Update No. 14 The Contractor is still continuing to work through final punch list items as the project moves closer to finalization. The concrete subcontractor, seeding subcontractor and other subcontractors still have work to be completed and will be … Continue reading
Construction Update 11
The Contractor is currently working on several large scale portions of the project. Currently the contractor is working on 1st Street North between 6th Avenue North and 8th Avenue North. The area between 6th Avenue North and Langer Avenue is … Continue reading
Construction Update No. 7
Asphalt Asphalt paving is scheduled to begin in the Morningside Drive area on Wednesday morning, September 18, 2013. The asphalt contractor will first place an asphalt leveling course on the streets in the Morningside Drive area to smooth out any … Continue reading
Construction Update No. 5
Televising and cleaning of the sanitary sewer mains is currently underway throughout the City of Casselton. The north side of the City should be completed in the very near future. During this time, you may hear some noises coming from … Continue reading
Construction Update No. 4
A majority of the milling has been completed. The contractor will now perform asphalt patches throughout the City in areas that are noted as problematic with the subgrade. There will also be some replacements of intersections to make sure that … Continue reading
Construction Update No. 3
Asphalt Paving The City has received a few questions and some curiosity from residents in regards to when the milled streets will be re-paved. As part of the project, the milling must first be completed. The milling for most of … Continue reading
Quick Update – Parking
The contractor has asked all residents in the residential areas of the north side of the railroad tracks to park off of the streets. Keeping cars off the street helps with the milling process which ultimately leads to a smoother, … Continue reading
Construction Update No. 2
Project Information & Timeline The project will begin on Tuesday July 16, 2013 with Industrial Builders Incorporated moving equipment in to begin milling the streets. This process should take approximately 8-9 days depending on the weather. The plan right now … Continue reading
Welcome – Construction Update No. 1
Welcome to the Sewer and Street Improvement District No. 25 project web page! This blog has been put together and will be updated in order to keep residents informed of construction activity taking place in your neighborhood and throughout the … Continue reading